Reagan National Airport
New Parking has opened at Reagan National
Due to the demand for parking at Reagan National, we are adding over 1400 spaces to the airport's existing parking garages by building an additional level on two parking garages. This project began in 2008 and is nearing completion.
Current Project-Related Construction Alerts
|
A NEW, SEPARATE ENTRANCE TO GARAGE A IS OPEN FOR DAILY PARKING
|
Project Phases and Milestones
The project is now underway. Below is a description of the project's phases:
![]() |
Set up construction equipment near the parking garage. Vehicle traffic flow will be maintained but some lanes will be closed or realigned along the roadways adjacent to the garages. |
![]() |
Phase 1: Construct the first section of the new, fifth level of parking on Garage B/C which adds 72 new spaces to the total capacity of the Garage. Completed September 2008 |
![]() |
Phase 2: Construct the second section of the new, fifth level of parking on Garage B/C which adds 260 new spaces to the total capacity of the Garage. Completed February 2009 |
![]() |
Phase 3: Construct the final section of the new, fifth level of parking on Garage B/C which brings a cumulative total of 843 new parking spaces to the Garage. Completed Fall 2009 |
![]() |
Phase 4: Temporarily close one level of Garage A and construct a new, fifth level which will expand Garage A by 581 parking spaces when the project is complete. |