Airports Authority Awards Contract for Phase 2 of the Silver Line

Jun 29, 2015 - 02:45PM EDT
May Board Meeting Includes Next Steps of Phase 2; New Employees Added to Airports Authority Leadership Team
Read More

Airports Authority Issues Notice to Proceed; Begins Silver Line Phase 2

Jun 29, 2015 - 12:43PM EDT
Design/Build package scheduled to be completed July 2018
Read More

Airports Authority Announces Delay in Expected Completion of Silver Line Phase 1

Jun 29, 2015 - 11:44AM EDT
Approximately Eight Weeks Needed for Additional Testing, Adjustments
Read More

Silver Line Phase 1 Nears Substantial Completion

Jun 24, 2015 - 01:58PM EDT
Project on Track for November Completion Following Additional Testing and Project Work
Read More

Airports Authority Announces Update On Silver Line Phase 1 Progress

Jun 24, 2015 - 01:09PM EDT
The Metropolitan Washington Airports Authority announced Monday that additional tests are needed on Phase 1 of the Silver Line, focusing on software updates related to the Automatic Train Control System, before the project can be turned over to the Washington Metropolitan Area Transit Authority.
Read More

Four Teams Selected to Compete for Silver Line Rail Yard and Maintenance Facility Contract

Jun 24, 2015 - 10:37AM EDT
Competitive Process Ensures Lowest Pricing for Design-Build Project  
Read More

Airports Authority Statement Regarding Status of Silver Line Phase 1 Construction

Jun 24, 2015 - 10:32AM EDT
Below is a statement from the Metropolitan Washington Airports Authority regarding the status of construction on Phase 1 of the Dulles Corridor Metrorail Project. "The Metropolitan Washington Airports Authority and the Washington Metropolitan Area Transit Authority have concluded a review of the Silver Line Phase 1 Substantial Completion Submission from Dulles Transit Partners, and determined the contractor has not yet met the contract requirements for substantial completion.
Read More

Airports Authority Announces Silver Line Phase 1 Substantial Completion

Jun 24, 2015 - 10:20AM EDT
The Metropolitan Washington Airports Authority announced its concurrence Thursday with an April 9 Declaration of Substantial Completion for Phase 1 of the Silver Line Project to extend the Washington region’s Metrorail public transit system.
Read More

Airports Authority Issues Final Dulles Toll Road Revenue Bonds in Support of Silver Line and Receives Approval for TIFIA Loan

Jun 24, 2015 - 10:09AM EDT
Board of Directors Receives Update on Silver Line Financing and Construction, Changes in Air Service Reagan National and Dulles International
Read More

Airports Authority Announces Intent to Award Final Major Silver Line Phase 2 Contract

Jun 24, 2015 - 09:59AM EDT
Hensel Phelps Construction Co. Submitted Apparent Low Offerto Build Rail Yard and Maintenance Facility at Dulles International Airport
Read More

Silver Line Express Bus Service Begins July 26

Jun 24, 2015 - 09:53AM EDT
New Direct Service Will Connect Dulles International Airportto Metro’s Silver Line
Read More

Airports Authority Updates Status of Silver Line Metrorail Construction Project

Jun 23, 2015 - 01:17PM EDT
Design Changes Enhance Safety, Reliability, Environmental ProtectionWill Add Time, Cost; Will Not Impact Dulles Toll Road Rates  