The Airports Authority has issued the following contracting opportunities:
Construction Opportunities
IFB 25-26022: West Building Demolition, DCA
Description: The Contractor shall demolish the West Building located at 2509 Abingdon Drive at Ronald Reagan Washington National Airport (DCA). Work includes abatement and safety plans, utilities survey, demolition of entire building including foundations, utility cap/rerouting for continuation of services, etc, installation of new fill, asphalt/parking striping and surface lighting. The contractor shall salvage the slate roof tiles and other identified items.
Solicitation Issue Date: October 3, 2025
Due Date for Submissions: November 3, 2025
Amendments Issued: None
SLBE Requirement: 35%
Additional Information - See in MWAA Contract Lifecycle Management System
RFP-25-25569: Construct Taxiways W & W3 and Rehabilitate Taxiways Y & Y9, IAD UPDATED
Description: The Contractor shall provide all labor, materials, tools, equipment and supervision necessary to construct new Taxiways W and W3, and rehabilitate Taxiways Y and Y9 at Washington Dulles International Airport (IAD).
Solicitation Issue Date: October 1, 2025
Due Date for Submissions: November 10, 2025
Amendments Issued: One
SLBE Requirement: 25%
Additional Information - See in MWAA Contract Lifecycle Management System
IFB-25-24551: Electrical Feeders Installation & Replacement, IAD UPDATED
Description: The Contractor shall furnish all necessary labor, materials, tools, equipment, & supervision to provide turnkey construction for the installation of New Electrical Feeders & replacing existing Electrical Feeders at Washington Dulles International Airport (IAD). Work includes but not limited to the following:
1.) installation of two new 15kV parallel feeders designated PN-3 & PN-4 to increase the existing Medium Voltage (MV) distribution capacity.
2.) replacement of the existing 15kV feeders designated PW-1 & PW-2 originating from 15kV Switchgear lineups in IAD’s Utility Building East (UBE) & Utility Building West (UBW)
3.) replacement of the existing 15kV feeders designated PU-1 & PU-2 originating from 15kV Switchgear lineups in IAD’s Utility Building East (UBE) & Utility Building West (UBW).
Solicitation Issue Date: September 11, 2025
Due Date for Submissions: November 4, 2025
Amendments Issued: Five
SLBE Requirement: 25%
Additional Information - See in MWAA Contract Lifecycle Management System
RFP-25-25366: High Temperature Hot Water (HTHW) Temporary Boiler Lease and Tie-in, DCA UPDATED
Description: The Contractor shall provide a temporary dual fuel boiler rated at < 99MMBTU/hr and 80,000 to 100,000 pounds/hr steam at the central utility plant at Ronald Reagan Washington National Airport (DCA) for lease of up to four years. Work includes installation of all necessary piping, valves and connections, heat exchanger, gas line, power, controls, and etc., to be fully integrated into the Authority’s central plant and Building Automation System.
Solicitation Issue Date: August 25, 2025
Due Date for Submissions: November 3, 2025
Amendments Issued: Five
SLBE Requirement: None
Additional Information - See in MWAA Contract Lifecycle Management System
Design/Build Opportunities
None
Architectural & Engineering Opportunities
None
Services Opportunities
IFB-25-21917: Industrial Waste Treatment Operations Maintenance Services, DCA UPDATED
Description: The Contractor shall perform routine maintenance and cleaning at the Industrial Waste Treatment Operations (IWTO) and other sources at Ronald Reagan Washington National Airport (DCA), in accordance with Arlington County Code (Chapter 26, Article II) and the County Wastewater Permit No 0778.8 effective January 1, 2024.
Solicitation Issue Date: October 8, 2025
Due Date for Submissions: November 13, 2025
Amendments Issued: One
SLBE Requirement: None
Additional Information - See in MWAA Contract Lifecycle Management System
Goods and Equipment Opportunities
IFB-25-24107: Secure Badge Card Stock, DCA & IAD NEW
Description: The contractor shall supply and deliver Metropolitan Washington Airports Authority-specific printable secure identification badge proximity card stock for Ronald Reagan Washington National Airport (DCA) and Washington Dulles International Airport (IAD).
Solicitation Issue Date: October 28, 2025
Due Date for Submissions: November 19, 2025
Amendments Issued: None
SLBE Requirement: None
Additional Information - See in MWAA Contract Lifecycle Management System
IFB-25-24054: Mobile Lounge Wheel Hubs, IAD UPDATED
Description: The Contractor shall provide all labor, parts, and materials to produce seventy-six Mobile Lounge wheel hubs for delivery to Washington Dulles International Airport (IAD).
Solicitation Issue Date: October 23, 2025
Due Date for Submissions: November 14, 2025
Amendments Issued: One
SLBE Requirement: None
Additional Information - See in MWAA Contract Lifecycle Management System
IFB-25-22520a: Stocked Electrical Supplies, IAD & DCA UPDATED
Description: The Contractor shall provide and deliver lamps, ballasts & electrical supplies that are used in the Main Terminal, Concourses and interior/exterior buildings at Washington Dulles International Airport (IAD) and Ronald Reagan Washington National Airport (DCA) on an as-needed basis.
Solicitation Issue Date: October 16, 2025
Due Date for Submissions: November 7, 2025
Amendments Issued: One
SLBE Requirement: None
Additional Information - See in MWAA Contract Lifecycle Management System
RFP-25-25366: High Temperature Hot Water (HTHW) Temporary Boiler Lease and Tie-in, DCA UPDATED
Description: The Contractor shall provide a temporary dual fuel boiler rated at < 99MMBTU/hr and 80,000 to 100,000 pounds/hr steam at the central utility plant at Ronald Reagan Washington National Airport (DCA) for lease of up to four years. Work includes installation of all necessary piping, valves and connections, heat exchanger, gas line, power, controls, and etc., to be fully integrated into the Authority’s central plant and Building Automation System.
Solicitation Issue Date: August 25, 2025
Due Date for Submissions: November 3, 2025
Amendments Issued: Five
SLBE Requirement: None
Additional Information - See in MWAA Contract Lifecycle Management System
Concessions Opportunities
RFP-25-24520: Remote VIP Services Facility, IAD UPDATED
Description: The Airports Authority is seeking a contractor to develop, lease, and operate a Remote Very Important Person (VIP) Services facility, including performing security screening, processing, and transfer of VIP passengers and their baggage to and from commercial aircraft in accordance with government guidelines, airline check-in arrangements, and providing goods and services commonly available in a commercial airport terminal or VIP airport lounge at Washington Dulles International Airport (IAD).
Solicitation Issue Date: September 26, 2025
Due Date for Submissions: November 21, 2025
Amendments Issued: One
SLBE Requirement: 25% of facility design and construction
ACDBE Goal: 5% of concession operations
Additional Information - See in MWAA Contract Lifecycle Management System
Dulles Corridor Metrorail Project Opportunities
Project Overview - Dulles Corridor Metrorail Project
Phase One of the Dulles Corridor Metrorail Project constructed the new Metrorail Silver Line from the East Falls Church station on the Orange Line, through Tysons Corner and on to Wiehle Avenue in Reston. Phase Two will continue the line to Dulles International Airport and into Loudoun County.
Dulles Corridor Metrorail Project - Phase Two
Capital Rail Constructors, a joint venture of Clark Construction Group and Kiewit Infrastructure South, is the Metropolitan Washington Airports Authority's design-build contractor for Phase Two of the Dulles Corridor Metrorail Project, which will build 11.4 miles of track and six stations in Fairfax and Loudoun counties. Construction of Phase Two began in 2013 and will continue through 2018.
The following link will take you to the Capital Rail Constructors website where you can learn about subcontracting opportunities for Phase Two of the Dulles Corridor Metrorail Project:
Capital Rail Constructors Subcontracting Information
Additional Dulles Corridor Metrorail Project Contracting Opportunities
The Metropolitan Washington Airports Authority has issued the following additional contracting opportunities for the Dulles Corridor Metrorail Project:
None